Decision details

Former Thames Valley University Campus and Montem Leisure Centre Demolition

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To seek approval to a demolition budget for the empty buildings at the Former Thames Valley University site and Montem Leisure Centre.

Decision:

(a)  That a demolition budget of £4m be agreed to cover vacant buildings on the NWQ and the Montem Leisure Centre sites; and

 

(b)  That delegated authority be given to the Director of Regeneration, following consultation with the Leader of the Council, to agree the final procurement contracts.

Report author: Stephen Gibson

Publication date: 08/06/2018

Date of decision: 18/06/2018

Decided at meeting: 18/06/2018 - Cabinet

Accompanying Documents: