Britwell Regeneration Scheme - from Concept to Reality

Decision:

a)  Note the progress reported at Appendix B to the tabled report.

b)  Agree that a further update report be made to the Cabinet meeting on 21st November 2011.

 

Minutes:

The Cabinet was provided with an update on the progress for the delivery of the Britwell Regeneration Scheme.  Mansell Construction Services Limited had failed to deliver in terms of price at the second stage of the tendering process.  Consequently a retendering process was to take place, which would set the Scheme back by approximately six to eight weeks.

 

The Cabinet was informed that good progress had been made and the demolition of various sites was underway as planned.

 

Resolved:

 

a)  That the report be noted.

 

b)  That a further update report be made to the Cabinet meeting on 21st November 2011.