Minutes:
The PFI contract was an arrangement where the contractor took the risk of designing, building, financing and operating the three schools’ buildings. Value for money was recognised as a primary concern, given the length of the contract (30 years from its commencement in 2006) and this was addressed through effective contract management processes. Affordability could in theory be improved by reducing costs but PFI contracts were notoriously inflexible. The buildings were in effect paid for in a similar fashion to a mortgage, and funded by PFI Credits from the DfE, whilst the payments for the facilities management and other operational costs were index linked to inflation. All payments were consolidated in a Unitary Charge.
As a result, the ongoing cost consideration was the contracting of services. An intensive and tight specification was enforced by SBC, which could also use a deductions mechanism to reduce payments to service providers where services had not been provided in accordance with the contract. The Contract Manager held responsibility for this process. However, the length of the contract and the changes in local government funding which had occurred in that period could raise their own difficulties, especially given the relative absence of flexibility in the contract. One method of counteracting this was using the Council’s procurement purchasing power to obtain economies of scale in, for example, the purchase of utilities supplies which would reduce the unitary charge. Thus far, SBC had pursued the relatively easier savings and was now moving to the more challenging methods of reducing costs which would require difficult negotiations with the contractor; the contractor had protections in the contract that could limit these opportunities. The contractual process had caused SBC to pursue, initially at least, a less formal route as the best method of creating the environment for negotiating savings. Initial discussions had been held with equity holders as part of this process, and SBC would take an iterative approach to secure better terms.
In terms of refinancing, the overall cost of designing and building the 3 schools was approximately £45 million. Around 90% of this (£40 million) had been funded by the contractor as a bank loan at a fixed rate of interest. Given that the contract had been taken out prior to the credit crunch, traditional refinancing was not an option as the terms of lending were now more expensive. The debt could in theory be replaced with a Public Works Loan Board arrangement, but this had been investigated and the potential for savings was not deemed worth pursuing. Lower annual payments could be secured by extending the contract of the loan, but this would ultimately make the deal more expensive.
The Panel raised the following points in discussion:
Resolved: that
1. The ECS Scrutiny Panel would receive a financial statement on schools and any possible top slicing of funding to cover short falls in PFI funding.
2. The ECS Scrutiny Panel receive a report on the benchmarking of services in 2016 – 17.
3. The ECS Scrutiny Panel’s support for increased value for money in PFI contractual arrangements be noted.
Supporting documents: