The
Director of Finance and Resources (Section 151) introduced a report
that provided a summary of spend against capital budget for the
2019-20 financial year, as at the end of March 2020, and set out
the 2020-21 Capital Programme.
Members
were referred to the main items of Capital Programme expenditure
set out in the table in section 5 of the report.
The
Chair invited Members to comment and ask questions.
During
the course of the discussion, the following points were
raised:
-
A Member requested information regarding the
commercial rent received from the Council owned Odeon cinema in
Basingstoke. The Interim Head of
Financial Management agreed to circulate the commercially sensitive
information to the Committee outside of the meeting. It was confirmed that during the Covid-10 pandemic
the Council had continued to receive the commercial rents
owed.
-
Additional information was sought regarding the
procurement of a new refuse fleet and the cemetery extension
project. It was explained that refuse
fleet vehicles had an optimum lifespan, and the assets were
replaced on a revolving programme.
Refuse fleet vehicles had a 7-10 year life cycle, after which time
it became uneconomical to fix vehicles needing repair. In relation to the cemetery expansion, the
Committee was informed that the expansion was necessary to meet the
predicted increase in demand. It was
predicted that up until 2060 there would be a continuous 33%
increase in number of burials and cremations in Slough. In the prior years approximately £4 million
had been spend on new abatement equipment installed at the
crematory. The expansion had been
rolled out in three phases, with the final phase completing in the
2020/21 financial year.
-
A Member asked if the recent statement from the
Chancellor of the Exchequer had announced any funding for local
government to assist with the funding gap created by the impact of
Covid-19. The Director of Finance and
Resources (Section 151) reported that no additional funding had
been referenced in the recent statement. Local authorities were awaiting details of the
£500 billion allocation which had previously been announced
by the Chancellor.
-
It was queried if any of the refuse fleet were
electric vehicles. It was explained
that there were currently no electric vehicles. In 2017, when the fleet had previously been
replaced, there had been concern there was insufficient
infrastructure to maintain and repair electric
vehicles. The availability of
technology had now improved, so the purchase of electric vehicles
may be considered in the future.
Resolved –
(a)
That the report and revised 2020-21 budget, as set
out in Appendix C and D of the report, be noted.
(b)
That the Interim Head of Financial Management be
request to circulate information to the Committee regarding the
commercial rent received from the Council owned Odeon cinema in
Basingstoke.