Traffic management arrangements for Bath Road works
Provisional timeline for major highway works for A4 Bath Road projects
- Huntercombe Lane crossroads - Goldsworthy Way from 12 January to 31 March 2026.
- St Andrews Way to Elmshott Lane/Station Road from July 2026 to November 2026.
- Elmshott Lane Burnham Lane from November 2026 to May 2027.
- Burnham Lane to Dover Road from April 2027 to July 2027.
- Dover Road to Pitts Road crossing from June 2027 to April 2028.
- Tuns Lane to Montem Lane from November 2026 to May 2027.
- Montem Lane to Stoke Poges Lane from May 2027 to March 2028.
- Stoke Poges Lane to Wexham Roads from March 2028 to May 2028.
Please note:
- the programme may change and will be updated accordingly and
- the traffic management plans are subject to change at short notice.