A4 Cycle Lane

Traffic management arrangements for Bath Road works

Provisional timeline for major highway works for A4 Bath Road projects

  • Huntercombe Lane crossroads - Goldsworthy Way from 12 January to 31 March 2026.
  • St Andrews Way to Elmshott Lane/Station Road from July 2026 to November 2026.
  • Elmshott Lane Burnham Lane from November 2026 to May 2027.
  • Burnham Lane to Dover Road from April 2027 to July 2027.
  • Dover Road to Pitts Road crossing from June 2027 to April 2028.
  • Tuns Lane to Montem Lane from November 2026 to May 2027.
  • Montem Lane to Stoke Poges Lane from May 2027 to March 2028.
  • Stoke Poges Lane to Wexham Roads from March 2028 to May 2028.

Please note:

  • the programme may change and will be updated accordingly and
  • the traffic management plans are subject to change at short notice.