The new local plan for Slough

Timetable for the new Local Plan

Statement of Effect

This timetable for the Local Plan is brought into effect in accordance with Section 15B of the Planning and Compulsory Purchase Act 2004 (as amended).

The timetable sets out the key stages and timescales for the preparation of the Slough Local Plan and has effect from 30 June 2026.

Current timetable for the Local Plan (effective from 30 June 2026)

Stage of plan-making Date
Publication of notice of intention to commence Local Plan preparation 30 June 2026
Publication of notice of scoping consultation 30 June 2026
Scoping consultation: start date 13 July 2026
Scoping consultation: closing date 24 August 2026
Gateway 1: publication of self-assessment of readiness summary 31 October 2026
Publication of notice of proposed plan content and evidence 18 January 2027
Consultation on proposed plan content and evidence: start date 18 January 2027
Consultation on proposed plan content and evidence: closing date 1 March 2027
Gateway 2: date on which observations and advice will be sought from gateway assessor 24 May 2027
Publication of notice of proposed Local Plan consultation 11 October 2027
Consultation on proposed Local Plan: start date 11 October 2027
Consultation on proposed Local Plan: closing date 6 December 2027
Gateway 3: date on which observations and advice will be sought from the appointed person 2 June 2028
Submission of the proposed Local Plan to the Secretary of State for independent examination 21 June 2028
Adoption of the proposed Local Plan 20 December 2028

Additional consultations

The council does not intend to undertake any consultations in connection with the preparation of the Local Plan other than those required under Regulations 20, 23 and 27 of the Town and Country Planning (Local Planning) (England) Regulations 2026.

Supplementary plans

The council does not propose to prepare any supplementary plans alongside the Local Plan.

Keeping the timetable up to date

The council will keep the Local Plan timetable under review and update it as necessary to reflect any changes.

The timetable will be updated at least monthly where there are changes to the dates, and at key stages in the plan-making process in accordance with relevant regulations and guidance.

Availability of the Local Plan timetable

The Local Plan timetable is available to view on the Council’s website. It is also available for public inspection at Slough Borough Council, Observatory House, 25 Windsor Road, Slough, SL1 2EL during normal opening hours.

Copies of the timetable can be provided on request.

The timetable is also available in the Government’s approved data standard.

Published 30 June 2026
Page last updated 30 September 2026